How to prepare a Kansas City commercial building for floor coating

How to prepare a commercial building in Kansas City for floor coating: clearing the floor, heat and air, moisture checks, phasing and staff notices.

To prepare a commercial building in Kansas City for floor coating, clear the floor to bare slab, hold the space at a steady working temperature, keep water and traffic off it, and settle the phasing and return-to-use plan in writing before the first machine arrives. Most of the problems that show up on coating day were decided weeks earlier, so this guide is written to be worked through in order.

Decide the areas and the phasing first

Start with a floor plan and mark it up. Which areas are coated, and in what order? Which aisles, exits and dock doors must stay open while each area is closed? Can the whole floor close at once over a holiday or a shutdown, or does it have to be done a section at a time?

Where the floor is done in sections, the edges between them need a plan. The federal chemical resistant flooring specification places the surfacing in any one room or area in one continuous operation, with divider strips at the slab's structural control joints as one option (UFGS 09 67 23.14). Ask where the section lines will fall before the schedule is fixed.

After-hours and holiday work is available to fit the business's hours, and crew size is matched to the building and the schedule, so the phasing can follow your operation rather than the other way around.

Clear the floor: stock, racks and equipment

Every item on the floor is either moved, or worked around and protected. Decide which, item by item, and write it down. Stock, carts, mats and loose shelving usually move. Heavy machines, racking anchored to the slab and kitchen equipment on fixed connections often stay.

What stays affects the floor. The federal standard resinous flooring specification runs the floor under equipment unless the equipment base sits flush on the slab, and masks equipment that is installed before preparation starts (UFGS 09 67 23.13). A machine left in place leaves an uncoated footprint and an edge to detail around. Note on the plan who moves each item and when it comes back; that is settled job by job in the quote.

Know what is on and in the slab

Tell the contractor everything you know about the floor's history: old coatings, paint, sealers, tile, adhesives, past spills and areas that have soaked up oil. The federal thin film flooring specification treats surface contamination such as oils, fuels, fats and waxes as one of three main causes of early coating failure, and it has tile and mastic tested for asbestos before they are removed (UFGS 09 67 23.15). If you have old building drawings or a past survey, have them ready. How the slab itself is cleaned and profiled is on our page about concrete floor preparation for epoxy.

Heat, air and a dry building

Resin coatings are sensitive to temperature. The federal standard resinous flooring specification, for its own system, keeps the materials between 65 and 85 degrees F and wants the floor dry and no colder than 60 degrees F when the topping starts (UFGS 09 67 23.13). The product data sheet sets the limits for any other product, and in a Kansas City winter that can mean keeping a warehouse or shop heated that normally runs cold.

Steady heat matters as much as warm heat. A coatings manufacturer names heaters cycling on and off, direct sun on the slab and sun warming an uninsulated building as causes of outgassing, air pushed out of a warming slab that leaves bubbles in fresh coating (Outgassing and Outgas Bubbles).

Run the building at its normal service temperature and humidity before the moisture tests too; the ready mixed concrete association's guidance is to test under service conditions (NRMCA CIP 28). Fix roof leaks, and keep wash water and hoses off the slab in the days before work. See our guide to concrete moisture testing before epoxy.

Dust and fumes: what to plan for

Preparing a concrete floor is regulated dust work. Concrete contains crystalline silica, and the fine dust from grinding it can cause silicosis (OSHA Fact Sheet). OSHA's construction silica standard lists floor grinders as their own task, with water feed or the machine maker's dust collection system with a filter of 99% or greater efficiency, and HEPA vacuuming between passes indoors (29 CFR 1926.1153). Ask which control will be used and how the work area will be closed off from the rest of the building.

Fumes are a product question. The federal standard resinous flooring specification bars smoking and spark sources near the mixing of flammable materials and leaves protective gear to the product maker's recommendations. Get the safety data sheet for each product, plan ventilation with the contractor, and decide whether neighboring areas should stay occupied during application.

Protect what stays in the room

Before preparation starts, floors, fixtures and equipment that stay in the room are protected: machine bases, equipment legs, floor drains, wall bases and the edges of finished areas. Tools and materials are kept to the active area so the rest of the floor stays usable, and the work area is cleaned up at the end of each shift. The federal specification's own version of this protects adjacent surfaces and puts a protective covering under the materials where they are stored and mixed (UFGS 09 67 23.13).

Tell staff, tenants and deliveries

People are the part of the plan most often forgotten. Tell staff which areas are closed and when, post rerouted walking and forklift paths, move dock appointments away from closed bays, and let tenants or neighboring businesses know about any noise or ventilation. Crews wear company shirts in safety colors, so they are easy to pick out on site; tell your staff that too.

Agree a sample area and the finish

Settle the look and the texture before the whole floor is done. The federal standard resinous flooring specification builds a sample area first to set the standard for appearance and workmanship, and warns that glossy finishes can be a slip hazard when wet or oily, so grit is specified to suit the room (UFGS 09 67 23.13). More grit is safer underfoot and harder to clean, so walk the sample with whoever mops the floor.

Pick colors from the system's own range. The federal chemical resistant specification lists light grey, dark grey, red, blue, tan, brown, dark green and light green top coats for industrial resinous floors (UFGS 09 67 23.14). Mark aisle and walkway stripes on the plan. OSHA requires permanent aisles and passageways to be appropriately marked where mechanical handling equipment is used (29 CFR 1910.176), and stripes can be laid in a contrasting topcoat color as part of the system.

Plan the return to use

Foot traffic, wheeled traffic, equipment and washdown each come back on their own schedule, and that schedule comes from the product data sheet for the system used and the temperature on the day. As one example, the federal chemical resistant specification keeps traffic off its surfacing "for a minimum period of 48 hours" (UFGS 09 67 23.14); that is that specification's rule for its own system, not a general figure. The federal standard resinous flooring specification also covers the finished floor to protect it from later construction traffic. If other trades are working in the building, plan that protection too. Write the return-to-use dates into the schedule before work starts, and post them.

A one-page checklist

  • Mark up a floor plan: areas, order, open aisles and exits, section lines.
  • List each item on the floor as moved or protected, and who moves it.
  • Share the floor's history: coatings, sealers, tile, spills, oil-soaked areas.
  • Keep the building at service temperature and humidity, with steady heat.
  • Fix leaks and keep water off the slab before moisture testing.
  • Ask about dust controls and how the work area is closed off.
  • Get the safety data sheets and plan ventilation.
  • Notify staff, tenants and deliveries; reroute paths.
  • Approve a sample area for texture and color; mark stripes on the plan.
  • Put return-to-use dates in writing for foot, wheel and washdown traffic.

Building preparation questions

Do we have to empty the whole building?

No, only the areas being coated in each phase. Work is kept to the active area, and larger floors can be split into sections so the rest of the building keeps working.

Does the heat need to stay on?

Yes, steady heat, by the published guidance. A federal flooring specification sets temperature limits for both the materials and the floor, and a coatings manufacturer names heaters cycling on and off as a cause of bubbles in fresh coating.

How soon can forklifts go back on the floor?

When the product data sheet says so. The federal chemical resistant flooring specification keeps all traffic off its system for at least 48 hours, but that is its own rule, and other products and temperatures give other answers.

Who moves the equipment and racking?

That is settled in the quote. It varies from job to job, so the quote should list each item and say who moves it, who reconnects it, and when it comes back.

Sources

Share your schedule and floor plan

Send photos of the floor, a rough floor plan if you have one, and the days and hours each area can close. Read about commercial and industrial floors, or see our floor coating FAQ. Get a Quote