Why epoxy floor coatings peel or bubble: a Kansas City guide

Why an epoxy floor coating peels or bubbles: slab moisture, oil, weak surface concrete, poor prep and outgassing, explained for Kansas City buildings.

An epoxy floor coating in Kansas City peels when its bond to the concrete fails, most often from moisture vapor, oil in the slab, weak surface concrete or thin preparation, and it bubbles when air or moisture pushes up through the coating while it cures or after. Almost every cause lives in the slab, which is why the fix starts there too.

Peeling and bubbling are two different failures

Delamination, the coating letting go of the concrete, is a bond failure. Bubbles in a freshly applied coat are usually air leaving the slab while the resin is still soft. Blisters that show up months later on an older floor are a third thing and usually point to moisture. Start by matching what you see:

What you see Most likely cause Read
Coating lifting in sheets, clean underneath Contamination, moisture or too little surface profile Sections on oil, moisture and profile below
Coating lifting with a skin of concrete stuck to the back Weak surface concrete or laitance left in place Weak or dusty surface concrete
Peeling near doors, drains or in old oil spots Contamination or moisture concentrated in one area Oil and contamination; moisture vapor
Tiny bubbles, craters or pinholes in a new coat Outgassing from the concrete Bubbles and pinholes from outgassing
Raised blisters appearing on an older floor Moisture coming up through the slab Moisture vapor coming up through the slab

Moisture vapor coming up through the slab

Moisture is the failure the concrete industry writes about most. The ready mixed concrete association says slab moisture can "cause bond-related failures of non-breathable floor coatings" (NRMCA CIP 28). The ASTM relative humidity method lists the failures excess slab moisture can cause, including debonding and deterioration of "finish flooring and coatings" (ASTM F2170). The federal thin film flooring specification is blunter: "Improper MVE controls have produced numerous premature coating failures" (UFGS 09 67 23.15), where MVE means moisture vapor emission. A coatings manufacturer links moisture problems to "the blistering and peeling of coatings" (Moisture Mitigation).

Where does the moisture come from? The ready mixed concrete association names five sources: ground water rising through fine-grained soil by capillary action; water vapor from the soil, since the humidity of the ground under a slab on ground "will measure close to 100%" wherever the building is; a wet fill layer under the slab; mix water still in the concrete; and water that gets on the slab during construction. One of the association's main defenses is a vapor retarder directly beneath the slab, and an older slab poured without one has nothing to stop that soil vapor. Our guide to concrete moisture testing before epoxy explains how to measure it.

Oil, grease and other contamination in the concrete

Concrete is porous, and oil soaks in. The federal thin film specification names "high levels of surface contamination (such as oils, fuels, fats, and waxes)" as one of the three causes of early coating failure it wants owners to head off. A coating laid on oily concrete is bonded to the oil, not the slab.

The same specification gives a simple test: put drops of water on the suspect area. If they soak in, the surface is free of oil. If they "bead up and do not flatten out", the spot needs more degreasing. And there is a limit to what cleaning can do: a federal guide spec for chemical resistant floors says that where existing concrete is "deeply contaminated with oil or fat", a new concrete topping "should be shown and specified" (UFGS 09 67 23.14).

Weak or dusty surface concrete

The top of a slab is often its weakest part. Laitance is the weak, dusty skin that forms as concrete is finished, and the ASTM practice for preparing concrete by abrasion exists in part "to remove foreign materials and weak surface laitance" (ASTM D4259). Coat over it, and the coating can peel off with a thin layer of concrete stuck to its back.

Low surface strength is the first of the three failure causes in the federal thin film specification, which sets a minimum surface strength of more than 200 psi for its own system. That figure belongs to that specification; the coating manufacturer sets the figure for any other product.

Sealers, curing compounds and old coatings left in place

A new coating can only be as well bonded as whatever it sits on. The federal standard resinous flooring specification calls for the concrete to be "free of all paint, sealers, curing agents, oil, grease, moisture, dirt or any other contaminants" (UFGS 09 67 23.13), and the chemical resistant specification lists curing compounds and sealers among the slab conditions to check. The ready mixed concrete association advises avoiding curing compounds on floors that will receive coatings unless the coating maker says otherwise. A clear sealer can be hard to see, so a slab's history matters.

Too little surface profile

Surface profile is how rough the prepared concrete is, and resin needs that roughness to grip. Abrasion is meant to "create a surface profile in concrete" (ASTM D4259), and the profile a system needs is set on the International Concrete Repair Institute's Concrete Surface Profile scale, checked by comparing the floor with reference chips (CSP Profile Comparison). A slab that was only swept and rolled, or lightly washed, may have no profile at all. Our page on concrete floor preparation for epoxy covers the methods.

Bubbles and pinholes from outgassing

When bubbles appear in a freshly applied epoxy coat, a coatings manufacturer says "the most common culprit" is outgassing: air or gas escaping from the concrete and causing "blisters, craters, bubbles, or pinholes". It usually shows as a neat circle with a ridge or a bubble, sometimes with a pinhole at the bottom (Why Does My Epoxy Floor Have Bubbles?). Named causes include air-entrained concrete with excess air, and air moving in and out of the slab as temperature and barometric pressure shift.

The mechanism is simple. All concrete has some entrained air or porosity, and as the slab warms, the air inside expands and is pushed out. How much depends on how porous the concrete is and how much the temperature rises (Outgassing and Outgas Bubbles). The usual heat sources are direct sun on the slab, sun warming an uninsulated building, and heaters cycling on and off. The same manufacturer's advice for limiting it is timing: apply a coating meant to seal the concrete when the slab is warmest and its temperature is falling, so the resin is drawn into the pores instead of being pushed out.

The good news: outgassing bubbles "typically do not affect the bond strength of the coating". They are mostly a looks problem.

Coating a slab that is too new or too cold

New concrete is wet concrete. The federal standard resinous flooring specification does not start its topping until "the concrete has cured a minimum of 28 calendar days", and wants the floor dry and at least 60 degrees F when work begins (UFGS 09 67 23.13). The federal thin film specification records air temperature, floor temperature and humidity at the start of work and every hour after. Those are each specification's rules for its own system, and the product data sheet governs any other. The point is the same everywhere: a slab rushed into coating, or coated cold, is a common way to build in a failure.

What can be repaired and what has to come off

Outgassing defects can usually be fixed in place. Caught during priming, the area is re-primed or patched first; after the finish coats, the spots are sanded and patched, or the whole floor is recoated if the defects are widespread (Why Does My Epoxy Floor Have Bubbles?).

Peeling is different. The coating that has let go has to come off, the cause has to be found, and the slab has to be prepared again before anything new goes down. Our page on epoxy floor repair and recoating explains how the bond of an old coating is checked and when a new topcoat is enough. If the original system was the wrong one for the exposure, our guide comparing epoxy, urethane and polyaspartic floor coatings can help.

Peeling and bubbling questions

Why is my new epoxy floor full of tiny bubbles?

Most likely outgassing. Air in the concrete expands as the slab warms and pushes up through the wet coating, leaving bubbles, craters or pinholes. Sun on the slab and heaters cycling on and off make it worse.

Do bubbles mean the coating will peel?

Usually not. A coatings manufacturer says outgassing bubbles typically do not affect the coating's bond strength. Blisters that appear later on an older floor are a different matter and point to moisture coming up through the slab.

Can moisture really push a coating off concrete?

Yes. The concrete industry's guidance says slab moisture can cause bond-related failures of coatings that do not breathe, and a federal flooring specification says poor moisture vapor control has caused numerous premature coating failures.

How do I find out why my floor failed?

Look at the back of a peeled piece and test the bare slab. Concrete stuck to the back means the concrete surface was the weak layer; a clean back points to contamination, moisture or missing profile. Any moisture test has to be run on bare concrete, because the calcium chloride test is not for use over coatings.

Sources

Send photos of a failing floor

Send a wide photo of the floor, close photos of the peeling or bubbled areas, and if you can, a photo of the back of a peeled piece. Tell us how old the coating is and what the floor is used for. Get a Quote

Floor coatings in Kansas City

Ready for
a quote?

Get a Quote